Replacing aging water mains to improve reliability and reduce breaks

About the Project

Status: Construction Underway
Construction: October 2026 – March 2027

SAWS is replacing aging water mains that have experienced frequent breaks. The E. Hildebrand Avenue work is part of the 2023 Water Main Replacement Project 4.

Is construction happening near you?

E. Hildebrand Avenue

McCullough Avenue → Devine Road
Installation will take place along Hildebrand Avenue and Old Hildebrand Avenue, from McCullough Avenue to Devine Road.

Construction Project Summary

23-4005
Job Number
City Council District 1
Estimated Budget: $11,300,000
*Budget amount covers all project sites
Approx. Timeframe:
October 2026 – March 2027
CONSTRUCTION PROJECTS

What to Expect During Construction

Water and sewer infrastructure is often located beneath our streets.
While we work, construction may temporarily affect traffic, access or water service.

Lane & Street Closures

Temporary closures may be necessary as crews work safely beneath roadways.

Traffic & Detours

Construction may affect normal traffic patterns. Follow posted signs and allow additional travel time.

Property Access

Driveway or property access may temporarily change as construction moves through an area.

Water Service

If work requires a planned water service interruption, affected customers will be notified.

Traffic & Construction Maps

Construction Project Map

utility work ahead

🚦 Current Traffic Impact

Construction is underway along E. Hildebrand Avenue.

Work is currently focused on Hildebrand between McCullough Avenue and Shook Avenue. The McCullough and Hildebrand intersection has reopened to traffic, while construction continues east toward Shook Avenue.

Traffic Map

traffic map

Construction raising questions? Let’s clear things up.

Water and sewer construction can affect your neighborhood, commute and daily routine. Have a question or want to receive updates about a project in your area? We’re here to help.

Contact Cecilia Picazo at 210-233-3750 or [email protected], use the form below to ask a question, share a comment or sign up for project updates.

 


Project Update

Hildebrand Water Pipe Installation Continues Toward Gillespie

November 25, 2026

Crews continue installing new water pipe on Hildebrand between McCullough and Shook. So far, they have installed approximately 500 feet of pipe, extending past the Judson intersection. Work continues east toward Gillespie, where crews are excavating and installing pipe. Crews are also connecting new water service lines to businesses in the area.

The next phase of work will take place at the Shook intersection. The intersection is expected to close late December.

Previous Updates

November 20, 2026

Work continues on Hildebrand between McCullough and Shook. Crews are installing new water pipe and have already placed more than 200 feet of pipe underground.

Crews have completed the crosswalk work at the intersection of McCullough and Hildebrand.

trench platescrosswalk

fusing pipes

November 16, 2026

The intersection of McCullough and Hildebrand is officially open to traffic. Construction continues along Hildebrand, with work focused on the area east of McCullough to Shook.

Intersection Open

November 13, 2026

Crews installed new water pipe and connected it to the existing system at McCullough and Hildebrand. Work also began along Hildebrand between McCullough and Shook.

In the coming weeks, crews are expected to begin work at the Shook Avenue intersection, which will require an intersection closure.

street restoration

November 6, 2026

Crews are digging trenches and welding sections of pipe in preparation for installation. Local businesses remain accessible through posted detours.

trenchfilling trench

pipe

October 30, 2026

Construction is underway, with traffic controls and road closures in place near Hildebrand and McCullough and between McCullough and Shook. Access to local businesses is available through detours.

Crews are cutting the street and will soon excavate to install the new water main. Weather permitting, construction at the intersection of McCullough and Hildebrand (Phase 1) will be completed by the end of November 2026. Work on Phase 2, along Hildebrand between McCullough and Shook, is anticipated to be in effect through December 2026.

traffic controlconstruction

October 21, 2026

Starting today, October 21, 2026, crews will begin preliminary work along Hildebrand between McCullough Avenue and Shook Avenue to prepare for upcoming construction. This work may require temporary single-lane closures while still maintaining two-way traffic.

Full road closures will be installed early Monday morning, October 26, 2026, between approximately 3 and 4 a.m. near the intersection of McCullough Avenue and Hildebrand. Residents may notice crews and equipment in the area during these early morning hours.

potholingelectronic message board

October 15, 2026

Starting October 19, 2026, residents may notice crews working along Hildebrand between McCullough Avenue and Shook Avenue. Crews will perform small excavations to locate and mark underground utilities in preparation for upcoming construction. This work may require temporary single-lane closures while still maintaining two-way traffic. No full road closures are scheduled until October 26, 2026.

October 7, 2026

Electronic message boards were installed near U.S. 281, Stadium Drive and Devine Road, Devine Road and Old Hildebrand Avenue, and San Pedro Avenue and W. Hildebrand Avenue.

message boardmessage board

Customers may see activity in the area beginning October 1, 2026, as crews prepare for construction. This work will include installing project signs, marking underground utilities, and setting up electronic message boards to help keep the community informed.

Plan ahead, since temporary street closures may affect your commute. Electronic message signs will be posted in various areas in early October to provide advance notice with links for information or project updates.

Lane closures will start in late October as crews begin locating underground utilities. Construction is anticipated to begin on October 26, 2026. Once work starts, portions of Hildebrand will be completely closed 24 hours a day, 7 days a week.

The map at the top of the webpage shows the planned construction phases, including when and where full road closures will occur, so residents and businesses can better prepare for work in their area.

September 21, 2026

SAWS met with District 1 residents and businesses to discuss the upcoming project. The project will replace approximately 4,600 feet of water main, a little more than the length of six Towers of the Americas.

During the presentation, SAWS shared information about the project schedule, upcoming construction activities, contractor information, and what residents can expect in coming months. Attendees asked questions about how the work may affect their homes, neighborhood streets, and traffic in the area. District 1 Councilwoman Dr. Sukh Kaur also attended the meeting and shared information about construction activities and traffic impacts. Continue to visit this site for detailed, up-to-date traffic maps.

 

Community Meeting Presentation

community meetingconstruction

September 4, 2026

SAWS Board has approved the E Hildebrand Water Main Replacement Project. Join us at an upcoming community meeting to learn about the construction schedule, what to expect during the project, and how it may affect your neighborhood.

Thursday, September 17, 2026

SAWS Headquarters Customer Center Building (Tower 2) – 2800 US-281 N, San Antonio, TX 78212
Room CR-C145

6 – 7 p.m.

August 21, 2026

The 2023 Water Main Replacement Project 4 – E. Hildebrand Site was scheduled to go before the SAWS Board in September 2026. Additional details and timeline regarding the project will be shared when they become available.

Do you have a question about the 2023 Water Main Replacement Project 4 – E Hildebrand Site in your area? Join SAWS and contractors at a neighborhood meeting.

SAWS will be hosting a community meeting for District 1 residents affected by the 2023 Water Main Replacement Project 4 – E Hildebrand Site. Learn more about the construction process and have your questions answered by SAWS staff and contractors.

Thursday, September 17, 2026

SAWS Headquarters Customer Center Building (Tower 2) – 2800 US-281 N, San Antonio, TX 78212
Room CR-C145

6:00 PM – 7:00 PM

Do you take the bus?

See what’s ahead for the VIA Rapid Green Line. Explore the route, planned improvements, construction updates and project timeline, and find ways to stay informed and involved.

 

VIA Construction Updates

VIA bus