SAWS: Vista Ridge Pipeline - Tales From the Vista Ridge Underground
Aquifer Beaker

Edwards Aquifer

Aquifer Level 681.2'
10/22/18 - Official

The Edwards aquifer and its catchment area in the San Antonio region is about 8,000 square miles and includes all or part of 13 counties in south-central Texas.

Learn More »


image

Year-Round Watering Hours

Watering with an irrigation system or sprinkler is allowed any day of the week before 11 a.m. or after 7 p.m.

Learn More »


Close

Aquifer Level 681.2 | Year-Round Watering Hours

Log In

Pay Your Bill Online

Already registered? Log in now.

Forgot your password?

New User

My Account Page

No user account? No problem.

Sign Up Now


Close

The Not-So-Dark Underbelly of Vista Ridge

The 142-mile pipeline route includes 19 tunnels, spanning more than 2,500 feet — almost 1/2 mile of horizontal boring.


Vista Ridge Pipeline Project

August 21, 2017

Tales From the Vista Ridge Underground

When most people think about pipeline construction, they probably picture a long, open-cut trench with sections of pipe joined end-to-end.

Along most of the Vista Ridge pipeline's 142-mile route, that description holds true, as seen in this recent photo of construction along an easement in rural Burleson County:

image

But did you know several segments of the pipeline require tunneling deep beneath existing roads and other infrastructure? It's true. The pipeline route includes 19 tunnels in all, spanning more than 2,500 feet — that's almost ½ mile of horizontal boring!

One of those tunnels is currently under construction deep below Highway 281 near Bulverde Road. Here's a view looking down at the tunnel's east entrance from the surface:

image

And here's the view looking westward from the bottom of the entrance pit:

image

The tunnel is so long — 471 feet to be exact — that it requires the use of small "railroad cars" to remove the spoils:

image

Tunneling under the highway allows construction to proceed without digging up the existing roadbed, much to the relief of tens of thousands of commuters who traverse that route twice each day. Currently, 15 of the 19 planned tunnels are complete.

Vista Ridge Tunnel Factoids:

  • 19 tunnels.
  • 2,500 feet total — almost ½ mile!
  • 15 already completed.

 

 